Health Campus
Daniel & Pamella DeVos Center for Interprofessional Health


New classroom/lab building for the colleges of nursing, health professions, and computer information systems
- 166,271 square feet
- 5 story building plus lobby, penthouse, and roof patio
- Parking spaces below building
- 4 classrooms
- 6 active learning classrooms
- 3 computer labs
- 4 labs
- Culinary lab/Dietetic kitchen
- 50 plus offices for faculty, staff, and clerical support
- Conference rooms and study space
- Library learning commons with learn labs & reading room
- Small food service space
- Veterans Center
- Simulation Center with 24 standard patient rooms, Flex Sim OR room, student & faculty observation rooms, debrief rooms, classrooms, model living suite, collaboration practice lab, anatomy lab, 1 PE Sim training lab, & PA lab
Schedule
- Design: September 2016 – September 2018 (Separated in 3 bid packages)
- Construction: June 2018 thru May 2021
Architect: Fishbeck
Construction Manager: Pioneer Construction
335 Michigan Parking Ramp



335 Michigan Project
New parking ramp shared with Spectrum Health
- 6 Stories of parking: 2 below grade and 4 above grade
- Approximately 1200 parking spaces divided 50/50 between GVSU and Spectrum Health
- Entrance and exit located off Lafayette Ave
- Entrance and exit located off Prospect Ave
Schedule
- Design May 2017 – December 2017
- Utility work March 2018
- Construction June 2018-May 2021
Architect: Fishbeck
Construction Manager: Pioneer Construction