Allendale Projects


Service Building Addition – Phase 2

Future home of Facilities Services

Square Feet – 13,440

Construction Start – August 2017

Construction Complete – December 2017

 

Service Building Addition – Phase 1

Future home of Facilities Planning

Square Feet – 12,560 

Construction Start – March, 2017

Construction Complete – August, 2017

 

Performing Arts Center Addition

Square Feet – 47,000 

Construction Start – May, 2016

Construction Completion – July, 2017

Project:  East side expansion of Performing Arts

 

Mackinac Hall Unit-C Renovation

Square Feet – 1st Floor Roughly 3,000

                         2nd Floor Roughly 18,000

Construction Start – May, 2017

Construction Complete – August, 2017

 

Pierce St. Sidewalk

New 8’ Sidewalk along Pierce St., between 48th Ave and 42nd Ave

Construction Start – April, 2017

Construction Complete – June, 2017

 

Seidman, Swanson, Stafford and Kirkpatrick Living Center Renovation

Interior Renovations

Construction Start – May, 2017

Construction Complete – August, 2017

 

Maple, Oak and Pine Living Center Renovation

Interior and Exterior Renovations

Construction Start – May, 2017

Construction Complete – August, 2017



Page last modified October 27, 2017